Solar development data in Hill County, Texas
Public county project and grid context. This is not a lease-rate estimate, property listing, indication of parcel suitability, or evidence that an organization wants to lease a particular property.
Interconnection queue requests
Queue activity
Source: LBNL Queued Up interconnection queue dataset. Queue requests are proposals seeking interconnection; they are not planned or operating facility counts.
Active queue requests
Tracked requests currently marked active
Active requested capacity
Requested capacity attributed to this county
2019-2025 complete years
| Year | Tracked requests |
|---|---|
| 2019 | 4 |
| 2020 | 0 |
| 2021 | 7 |
| 2022 | 6 |
| 2023 | 1 |
| 2024 | 0 |
| 2025 | 0 |
Facility facts
Planned and operating facilities
Planned facilities
1,558 MW · EIA-860 final annual generator inventory
Operating facilities
467 MW · EIA-860 final annual generator inventory
Queue request status is not used as a substitute for facility construction or operating status.
Independent operating inventory
Large-scale solar facilities
U.S. Large-Scale Solar Photovoltaic Database (USPVDB)
Observed capacity
Source release 2026-04-14
Mapped site area
Converted from source-reported square meters
Latest operation year
Latest source record represented in this county
This inventory is shown separately from EIA generators and LBNL queue requests to avoid double-counting records across datasets.
Retirement facts
Facility retirements
The EIA-860 final annual generator inventory lists no retired solar facilities in Hill County.
Public record attribution
Organizations named in queue requests
| Organization | Queue requests | Capacity | Latest request year |
|---|---|---|---|
| High Noon Solar Project, LLC | 2 | 276 MW | 2021 |
| Hillsboro Solar Project LLC | 2 | 404.7 MW | 2022 |
| Mercury Solar, LLC | 2 | 409.6 MW | 2022 |
| Ash Creek Solar LLC | 1 | 417.7 MW | 2019 |
| BPL Files Solar | 1 | 148.7 MW | 2018 |
| Elawan Pitts Dudik Solar, LLC | 1 | 49.6 MW | 2018 |
| Gransolar Texas Ten, LLC | 1 | 85 MW | 2021 |
| Hill PV, LLC | 1 | 70.4 MW | 2023 |
| Hill Solar II, LLC | 1 | 201.4 MW | 2022 |
| Hill Solar I, LLC | 1 | 405.7 MW | 2021 |
| Leitsol LLC | 1 | 98.4 MW | 2021 |
| Mercury II Solar, LLC | 1 | 206.1 MW | 2021 |
A name in an interconnection queue request does not mean the organization is seeking land in this county or has an interest in a particular parcel.
Infrastructure context
Grid infrastructure context
Source: HIFLD electric power transmission lines.
Transmission in county
Highest recorded voltage
Nearest line to county center
County infrastructure does not establish available grid capacity. A specific project requires parcel-level engineering and an interconnection study.