Development signal · Ellis County, TX · FIPS 48139

Battery storage development data in Ellis County.

Public county project and grid context. This is not a lease-rate estimate, property listing, indication of parcel suitability, or evidence that an organization wants to lease a particular property.

County-specific public records

Development activity

Active projects

10

Tracked public records currently marked active

Active capacity

2,619 MW

Capacity attributed to this county

Nearest active project

Not available

County-centroid distance, not parcel distance

Five-year public queue activity

YearTracked requests
20222
20232
20240
20257
20260

Public record attribution

Organizations named in public development records

OrganizationProjectsCapacityLatest request year
Kickstart Infrastructure LLC62,031 MW2025
BT Wilson Storage, LLC1125.7 MW2023
Cumulus Grid, LLC1210.7 MW2022
Desert Willow Energy Storage, LLC1154.4 MW2021
Edgewater Battery Storage LLC150 MW2019
Galaxy Solar 2, LLC1201.9 MW2025

A name in an interconnection record does not mean the organization is seeking land in this county or has an interest in a particular parcel.

Infrastructure context

Grid infrastructure context

Transmission in county

341 miles

Highest recorded voltage

345 kV

Nearest line to county center

5 km

County infrastructure does not establish available grid capacity. A specific project requires parcel-level engineering and an interconnection study.